Most factories answer this question with a feeling: one machine for each building, or one machine for every 20,000 m², or whatever the last supplier proposed. The result is either three machines idling in three buildings at once, or one machine that never finishes the route before the shift starts.
Machine count is arithmetic, not taste. The method below needs four numbers from your own site and the published productivity of the machines you are comparing. At the end it produces a count, a shift plan, and a way to prove both in a week.
1. Why "one machine per building" is the expensive default
Counting buildings feels safe because each building has a door and a person. But a machine is paid for by the hour it works, not by the building it parks in. Three machines in three half-empty buildings consume three purchases, three operators, three service contracts, and three sets of batteries — while each machine sits idle for most of its shift.
The opposite mistake is just as common: one machine sized by floor area alone, with no allowance for passes, docks, or traffic. That machine works a full shift, covers the main aisles, and still leaves the perimeter dusty — which is exactly the zone auditors photograph.
The rule: size the fleet by area-passes per cleaning window, then check that each machine's width, turning radius, and runtime can physically execute that plan.
2. Four numbers to collect before you talk to a supplier
2.1 Cleanable floor area — not building area
Subtract racking footprints, machine bases, columns, mezzanine structures, and permanent storage blocks from your floor plan. The cleanable share typically runs 55–70% in production plants, 45–55% in dense warehouses, and 75–85% in open logistics halls. A plant of 20,000 m² often has only 13,000 m² of floor a sweeper can actually reach.
Walk the routes with a laser distance meter or a phone GPS app and write down segment lengths. Drawings lie; pallet positions change every quarter.
2.2 Passes per shift — the multiplier everyone forgets
One pass is rarely enough. Main aisles see one pass, cross aisles one, but loading docks and perimeter zones usually need two or three because tire tracking and wind-blown dust return within hours. If a zone needs two passes, its area counts twice in the workload.

Fig. 1 — A600 at a textile market forecourt: four side brushes widen effective coverage per pass, which is the number that matters when the same area must be swept twice a day.
2.3 Soil load class — L, M, or H
Soil load decides how often the machine stops, and stops are what nominal productivity ignores.
| Class | Typical site | What the operator sees | Effect on plan |
| L — light | Sealed floor, packed warehouse, electronics | Fine dust, few cardboard scraps | Derating near 0.75; one bin dump per 2–3 h |
| M — medium | Assembly, food packaging, textile | Cardboard, film, foot traffic dust | Derating near 0.65; bin dump every 1–2 h |
| H — heavy | Foundry, sand, slag, outdoor carry-in | Grit, chips, wet patches at doors | Derating near 0.55; bin dump 2–3 times per hour |
2.4 The cleaning window — hours you actually have
A shift is not a window. If cleaning must be finished before the 07:30 start, the window is two hours, not eight. If forklifts keep crossing the main aisle, the usable window shrinks again. Write the window down in hours and treat it as a hard constraint — it decides machine count more often than area does.
3. From nominal to planning productivity
Published productivity is measured on clean, open, dry floor with no stops: width × speed, theoretically. It is a fair comparison between models and an unfair plan for a real plant. Apply a derating factor K:
| Model | Sweeping width | Nominal productivity | Planning at K = 0.65 | Debris bin | Water tank | Runtime |
| A300 | 1,150 mm | 5,580 m²/h | ~3,600 m²/h | 80 L | 75 L | 2.5–3 h |
| A600 | 1,900 mm | 9,500 m²/h | ~6,200 m²/h | 180 L | 60 L | 4–4.5 h |
| A900 (lithium) | 1,950 mm | 16,000–22,000 m²/h | ~10,400–14,300 m²/h | 240 L | 300 L | 5–6 h |
| Thunder God AMR | — | 2,750 m²/h | ~1,800 m²/h, unattended | Auto discharge | Auto refill | Multi-shift, no driver |
Read the table this way: K = 0.75 for open halls with long straight aisles, 0.65 for mixed production, 0.55 for dense racking or heavy soil. The AMR row is different in kind: it is slow per hour but runs without an operator and without a shift boundary.
4. Worked example: a 20,000 m² plant, one shift
A metal components plant has 20,000 m² under roof, 65% cleanable — 13,000 m². Main aisles and cells get one pass; docks and perimeter get two.
Sizing card — 20,000 m² plant
Cleanable area13,000 m² (65%)
Area-passes9,100 × 1 + 3,900 × 2 = 16,900
A600 machine-hours16,900 ÷ 6,200 = 2.7 h
Add stops (+15%)≈ 3.1 h
A300 machine-hours16,900 ÷ 3,600 = 4.7 h → 5.4 h with stops
DecisionOne A600, one operator, one shift, ~35% buffer
The A600 finishes inside a six-hour window and keeps enough margin for a water refill and two bin dumps. The A300 would also fit on paper, but at 2.5–3 hours per charge and a 75 L tank rated for 60 minutes of spraying, it needs a battery swap mid-route — acceptable if your cleanable area is closer to 8,000 m², tight at 13,000 m².

Fig. 2 — A300 handover at a food plant. Compact machines like this fit small cleanable areas; the same unit becomes a bottleneck the moment the area-passes double.
5. Worked example: 50,000 m², two passes, and a night shift
The same arithmetic on a larger site produces a different answer. 50,000 m² at 60% cleanable gives 30,000 m². Two passes on everything is 60,000 area-passes.
A600 alone: 60,000 ÷ 6,200 = 9.7 h, plus stops ≈ 11.2 h — more than one shift, so a second shift or a second machine is mandatory.
A900 alone: 60,000 ÷ 10,400 = 5.8 h, plus stops ≈ 6.7 h — fits a long single window, helped by the 240 L bin and 300 L tank that reduce stop frequency.
Hybrid: the AMR takes 7,000 m² of repetitive open floor overnight (14,000 area-passes ÷ 1,800 ≈ 7.8 h, unattended), while the A900 covers production aisles and docks (46,000 ÷ 10,400 ≈ 4.4 h).
The hybrid wins when labour is scarce, not when capital is scarce. It converts cleaning hours into overnight hours, and it keeps the driver on the routes that need judgment — edges, blind corners, wet patches at doors.

Fig. 3 — A900 on an outdoor road: 1,950 mm width pays back only where the route is long and straight; the same machine struggles in a 2.3 m aisle.
6. The bottlenecks that quietly add a second machine
Area-passes give you machine-hours. Stops decide whether those hours fit in the window. Three stops dominate:
Water
A300 carries 75 L and A600 60 L, both rated at 60 minutes of spraying per fill. Run dust suppression continuously and you refill once an hour. Place water points within two minutes of the route; a refill that requires a detour costs 8–12 minutes each time, and five refills erase an hour of planned work.
Debris bin
80 L, 180 L, and 240 L are not marketing numbers — they are stop frequencies. In H-class soil, an 80 L bin can fill before the water tank empties. Two to three dumps per hour is normal on foundry sand; budget the minutes.
Charging
Runtime is 2.5–3 h (A300), 4–4.5 h (A600), and 5–6 h (A900). If the window is longer than the runtime, the answer is a battery swap or opportunity charging, not a bigger machine.
Decision rule: if measured lost time exceeds 20% of the shift, add a machine or a second shift. Buying a wider machine to outrun stops usually fails — the stops travel with the route, not with the model.
7. One wide machine or two narrow ones?
Width is the most overrated specification in sweeping, because width only pays where the route allows it.
Wide (A900 class)
1,950 mm width, 2,310 mm turning radius, 1,146 kg, 2,650 × 1,950 × 2,560 mm. Wins on open yards, long roads, and halls above roughly 15,000 m² of cleanable floor. Check door widths, ramp capacity, and slab loading before ordering.
Narrow (A300 / A600 class)
A300: 1,150 mm, 320 kg, climbs 20°. A600: 1,900 mm, 1,100 mm turning radius, 590 kg, climbs 35°. Wins where doors, lifts, and mezzanines break the route into short segments.
Two narrow machines also buy redundancy: one breaks, the other still finishes the docks. One wide machine concentrates risk on a single operator and a single battery pack.
8. Prove the number before you sign
A sizing table is a hypothesis. A trial week is the experiment. Mark routes, run the candidate machine, and log four things every day.
Route area and passes — measured, not copied from the drawing.
Start and stop times — including every bin dump, water refill, and charge.
Completed passes — how much of the plan the window actually swallowed.
Operator notes — where the machine had to reverse, lift a brush, or slow down.
Acceptance numbers: achieved productivity at or above 85% of the planning table, and lost time below 15% of the window. If either fails, lower K and recalculate before adding machines — the shortfall is more often a route design problem than a machine problem.
Put the same numbers in the purchase order: "the machine shall complete route A (X m², two passes) within 3.5 hours with one water refill and two bin dumps." That sentence is worth more than any brochure figure.

Fig. 4 — Thunder God GT working an empty production hall. The value of an AMR is not its hourly rate but the hours it adds outside the shift window.
9. Frequently asked questions
1. How many square meters can a ride-on floor sweeper clean per hour?
Nominal figures are 5,580 m²/h for A300 (1,150 mm), 9,500 m²/h for A600 (1,900 mm), and 16,000–22,000 m²/h for A900 (1,950 mm). Plan at 55–75% of those numbers depending on obstacles and soil.
2. How many floor sweepers does a 20,000 m² factory need?
3. Should I use building area or cleanable floor area?
Cleanable floor area — building area minus racking, machine bases, columns, and storage. The gap is often 30–45%.
4. What derating factor is realistic?
5. Is a wider sweeper always cheaper per square meter?
No. Width only pays where aisles, doors, and turning space allow it. A 1,950 mm machine needs a 2,310 mm turning radius and weighs 1,146 kg.
6. Can a cleaning robot replace a ride-on sweeper?
It complements one. At 2,750 m²/h the AMR is slower, but it runs unattended, refills and discharges automatically, and works outside the shift window.
7. How often does the water tank need refilling?
8. How long can each model run on one charge?
2.5–3 h for A300, 4–4.5 h for A600, 5–6 h for A900. Longer windows need a swap plan, not a bigger machine.
9. Can one operator run two machines?
10. How do I verify the count before buying?
One trial week on marked routes, with daily logs of area, passes, stops, and charging. Accept at 85% of planning productivity and under 15% lost time.